Grand Opening Countdown and Timeline Planner

Author: First published

Task date = opening date minus a lead time in days. The lead times are the editorial desk's own planning defaults, not official or industry standards, and every one can be edited. No agency publishes lead times for permits, so ask your permit office how long yours take.

Countdown planner

Enter your opening date. The list updates as you type, is saved in the page address, and nothing leaves your browser.

Your opening

Format: year-month-day if your browser shows a text box.

1 means a single day.

Edit lead times (days)

Each number is the number of days before (or after) the date named in its label. These are editorial planning defaults. Change any of them to match what your own offices and suppliers tell you.

Your dated task list

How the countdown planner works

Every task has an anchor date and a number of days. The planner subtracts (or adds) that number of days from the anchor and sorts the results into seven streams: permits and paperwork, supplies, staffing, marketing, soft opening, event day and follow-up.

Task date
task date = anchor date - lead time (days)      for "before" tasks
task date = anchor date + lead time (days)      for "after" tasks
last event day = opening date + (event length - 1) days
anchor date
the opening date, the soft opening date, or the last event day, as named for each task
lead time
an editable planning default in whole days
event length
the number of days your opening event runs

Worked example

Given: Opening date 2027-06-12; Retail shop, no soft opening, one-day event; Default lead time for "Ask your city or county permit office which permits and licences apply to your business and how long each takes": 120 days before.

  1. Subtract the lead time from the opening date: 2027-06-12 - 120 days = 2027-02-12
  2. A marketing task with a 7-day lead time: 2027-06-12 - 7 days = 2027-06-05
  3. A follow-up task 7 days after the last event day: 2027-06-12 + 7 days = 2027-06-19

Answer: Each task gets its own date. Example numbers only; use your own opening date.

The default lead times

Editorial planning defaults (editable above; not official or industry standards)
StreamTaskDefault (days)Counted from
Permits and paperwork Ask your city or county permit office which permits and licences apply to your business and how long each takes120 beforeopening date
Permits and paperwork Check that business registration, tax ID and insurance are in place90 beforeopening date
Permits and paperwork Ask whether signs, banners, music, sidewalk use or a temporary event need approval where you are60 beforeopening date
Permits and paperwork Ask your local health department about food-service inspection and scheduling60 beforeopening date
Permits and paperwork Confirm every permit and licence you need is in hand and displayed as required14 beforeopening date
Supplies Set your opening budget with the budget estimator and collect quotes90 beforeopening date
Supplies Order printed items such as flyers and signs, after proofing the text35 beforeopening date
Supplies Confirm food and drink suppliers and your first orders21 beforeopening date
Supplies Receive stock and finish displays and pricing14 beforeopening date
Supplies Prepare your booking process, supplies and equipment checks14 beforeopening date
Supplies Arrange event supplies such as decor, tables and giveaways21 beforeopening date
Supplies Do a final walk-through and set up the space2 beforeopening date
Staffing Decide the roles you need for opening day and how many people fill each45 beforeopening date
Staffing Confirm staff and helpers and set their shifts30 beforeopening date
Staffing Hold a training or practice session10 beforeopening date
Staffing Share the event-day schedule and who does what3 beforeopening date
Marketing Settle your message and your offer, including its end date and any conditions42 beforeopening date
Marketing Draft the flyer or announcement text with the flyer text helper35 beforeopening date
Marketing Announce the date on your own channels, such as social media and email28 beforeopening date
Marketing Invite neighbours and nearby businesses, and start handing out flyers where you have permission21 beforeopening date
Marketing Send a reminder with the date, time and address7 beforeopening date
Marketing Post the last reminder1 beforeopening date
Soft opening Invite your soft opening guests7 beforesoft opening date
Soft opening Soft opening day: run it like a normal day and note what goes wrong0 beforesoft opening date
Soft opening Review your soft opening notes and fix what you can before the public opening2 aftersoft opening date
Event day Opening day: doors open and the event schedule begins0 beforeopening date
Event day Last day of your opening event0 afterlast event day
Follow-up Thank guests and helpers by message or post1 afterlast event day
Follow-up Review what worked, what it cost against your budget and what to change7 afterlast event day
Follow-up Plan your next promotion or follow-up offer14 afterlast event day

Every default is stored in the site's tool data file with its source and date. The values are the desk's own planning conventions; the SBA launch guide only informs which kinds of task exist.

Assumptions and limits

  • It makes no claim about how long permits, inspections or deliveries take. Those are set by the offices and suppliers you deal with.
  • It is not an "industry standard" schedule and does not say whether a date is realistic for your city or your business.
  • It does not check legal compliance. Confirm every requirement with the issuing office.
  • Dates are calendar dates, with no time of day. The calendar file creates all-day entries.

Next: set a budget with the budget estimator and word your announcement with the flyer text helper.

Quick answers

Are these lead times official?

No. They are planning defaults chosen by the editorial desk so the list is not empty. Nothing here is an industry standard, and a default is not a promise that a date is realistic for your city. Edit any of them in the lead-time section.

How long do permits take?

It varies by place and by permit, and this tool does not know. Ask your city or county permit office how long each one takes, then enter that number in the lead-time section. The permit tasks are reminders to ask, not predictions.

What if a date is already in the past?

The task is marked as a date that has already passed. That is not a verdict that you are late. Move the opening date, shorten the lead time if the real task is quicker, or drop the task.

Does it check that I am legally ready to open?

No. It is a reminder list, not legal, tax or licensing advice. Confirm requirements with the issuing offices where you are.

Is anything saved or sent?

No. It runs in your browser. Your entries are copied into the page address so you can bookmark or share the plan; anyone with that address sees your entries.

How do I get the plan into a calendar?

Use the calendar file button. It builds an .ics file in your browser with one all-day entry per task, which most calendar apps can import.

Where this comes from

  1. U.S. Small Business Administration: Launch your business (the steps owners take before opening) (sba.gov) Accessed 2026-11-17. Used only for which kinds of task exist, not for any timing.